  Schedule of Works 
 
 
 
 
 

Schedule of Works

This is a typical schedule of works that are carried out, each situation will be different to some extent.

  • Planning Consent - Design, Change of Use Certification.
  • Remove Garage door and infill with matching brickwork.
  • Fit matching window to garage opening.
  • Knock through opening to property and fit internal door.
  • Line, insulate and plaster walls and ceiling.
  • Construct floor with DPC membrane.
  • Fit radiator(s).
  • Fit skirting board and architraves.
  • Build cupboard around fuse box (if required).
  • Board roof void and insulate.
  • Fit new consumer unit (if required).
  • Provide Insulation/Ventialation calculations with 'Part P' and GAS SAFE Certificates.